Method Statement for Concreting of Raft Foundation
1. TITLE
Method Statement for the Concreting Works of Raft Foundation.
2. SCOPE OF WORKS
2.1
General Description
·
The
scope and purpose of this method statement is to outline the general
requirements and precautionary measures which should be taken into
consideration during concreting works of raft foundation and to ensure that
works are according to the drawings, standards and project specification.
2.2
Plant and Equipment
§
Concrete Mixer
§
Concrete Pump and standby
§
Tower Lights
§
Vibrators with standby
(Diesel & Electric)
§
Masonry trowels and other
hand tools
§
Concrete Power Trowel
§
Air Compressor
§
Concrete Hopper/ Bucket
§
Mobile/ Tower Cranes
§
Surveyor equipment
(level, Total station)
2.3
Materials
S.N
|
MIX GRADE
|
CONCRETE LOCATION
|
APPROVED MIXED DESIGN
|
1
|
C50
| Raft foundation | 50 Mpa with GGBS + MS |
SRPC20 | Blinding | Sulphate Resisting Portland Cement |
S.N
|
Material
|
Reference
|
STATUS
|
1
|
Steel reinforcement
|
||
2
|
Spacer & chamfer
|
||
3
|
Formworks
|
||
4
|
Tie wire
|
||
5
|
Polyethylene sheet
|
||
6
|
Release agent
|
||
7
|
PVC Waterstop
|
||
8
|
Swellbar
|
||
9
|
Curing compound
|
||
10
|
Hessian cloth
|
2.4 Site
Planning and Preparation
2.4.1 Site Management Plan and
Access Route
·
Upon receiving construction drawings, all concreting routes / locations will be set out and marked routes
plan and access shall be divided by geographical zones. The information will be
provided to the construction team for implementation.
2.4.2
Permits
·
Concreting Works permits
should be secured ahead of time from HSE Department.
2.4.3
Communication
·
Communication on site
will be by GSM mobile phones.
2.5.1
Pre-activity
Meetings
Coordination between different disciplines will be done prior to
commencing the concreting of particular structure based on the submitted work for inspection, Toolbox meeting should be conducted based on the approved method statement & risk assessment by the execution team. A pre-activity meeting will be held in order to
provide the following information:
·
The location of the
structure to be concreted, particular grid, type, area, volume etc.
·
All necessary inspection to
be performed for concrete works,
·
Related Interfaces,
coincidences and integration with all partners involved.
·
Related non-conformance, Technical
query, Technical deviation or concession request.
·
Ensure shop drawings are in
place and approved Released for Construction Drawings.
The
pre-placement activity meeting Safety task analysis risk reduction talk, has to be set to assign all tools required, rate of pouring,
vibration and finishing procedures, staff requirements, testing specialties,
traffic flow, number of pumps, emergency plans if any, etc.
2.5.2
Scheduling
The
concreting shall be scheduled well in advance to allow the control of geometry,
block-outs, insert, embeds, reinforcement and other activities.
A Concrete
Requisition shall be prepared by the Site Engineer. The Site Engineer receives
from Project Engineer 3 days look ahead concrete requirements with all data
related to the pour to prepare a complete and accurate concrete in advance
schedule as required by the concrete supplier.
The
concrete schedule will be verified for every next day by the Construction
Manager and coordinate with QA/QC requirements and approvals, prior sending to
the Concrete supplier.
On the day
of the pours, concrete orders shall be confirmed; the engineer in charge of the
pour confirms each pour requirement and readiness with the concrete coordinator
and the concrete coordinator confirms the same (make the order) with the
Concrete supplier.
Any
changes / amendments / deletions to the previously prepared concrete
requisition schedule shall be forwarded to the concrete coordinator without
delay. The concrete coordinator shall then amend the requisition to reflect the
actual concrete activities and, when confirming the order with the Concrete
Supplier, he shall make sure that the confirmation includes the latest
information as amended.
2.5.3
Work Sequence
2.5.3.1
Ground
Preparation
·
As per approved drawings, ground will be excavated aligned
with the markings placed by a licensed certified surveyor level and clean the
area as per given rock surface level.
·
Shutter
will be place aligned with the marking points placed by licensed certified
surveyor.
2.5.3.2
Blinding
·
Subsequent completion of the excavation, once the third party
Geotechnical had a site report stating that the soil could eliminate the
compaction due to the rocky property, will be cleaned, remove any loose
materials to be ready in applying the anti-termite.
·
Formwork for the blinding will be laid; as per the approved shop drawings
with the help of surveyors and sides of the shuttering will be supported with
the steel nails with end cap/ rebar cap. Surveyor will mark finishing levels of
the concrete on the formwork with nails.
· A certified technician from the approved Third Party
applicator will apply the Anti-termite solution and lay 1000 Gauge
polythene sheet prior to blinding.
·
Anti-termite treatment will be applied inside the formwork area by
approved applier in the presence of client/consultant if requested. (Please
refer to Method Statement of Anti-termite approval).
·
After application of anti-termite allow a gap of 1 hour prior to a pour
blinding.
·
Concrete of approved mix will be ordered after getting approval from the
client representative, and will be placed by means of pump or chute.
·
All the quality control checks for the concrete placement will be done,
before the placement with the help of laboratory technicians.
·
Final levels of the concrete will be rechecked with the help of
surveyor.
·
Compaction of blinding concrete will be done using a rigid metal or wood
performed in a vertical stroke.
·
One set of 150 mm cubes of any particular mix shall be taken by the
contractor every 100 m3 of concrete and/or once a day at least. Refer to appendix 6.2 Inspection and Test Plan
·
Blinding concrete shall have a minimum cube crushing strength of 20
N/mm2 at 28 days.
·
Continuous curing of newly casted blinding shall be properly done for at least
3 days consecutively.
2.5.3.3
Water Proofing
·
Ensure that the concrete substrate is well leveled and free of damage
prior to receive the waterproofing system, otherwise proper repair shall be
done.
·
Once blinding is cleaned and prepared for waterproofing, a certified
waterproofing mason will apply water proofing primer then lay membrane as per approved
separate method of statement.
2.5.3.4
Screeding
·
Damp proofing membrane using 1000 gauge polyethylene sheet will be
placed above membrane prior to screed.
·
Subsequent completion of the waterproofing once approved as per
application. Formwork will be placed aligned with the marking points placed by
the surveyor.
·
Concrete of approved mix will be ordered after getting approval from the
client representative, and will be placed by means of pump or chute.
·
All the quality control checks for the concrete placement will be done,
before the placement with the help of laboratory technicians.
·
Final levels of the concrete will be rechecked with the help of
surveyor.
Ø One set of 150 mm cubes of any
particular mix shall be taken by the contractor every 100 m3 of concrete and/or
once a day at least.
·
Screeding concrete shall have a minimum cube crushing strength of 20
N/mm2 at 28 days.
·
Continuous curing of newly casted blinding shall be properly done for
at least 3 days consecutively.
2.5.3.5
Steel Reinforcement Fixing
·
Steel reinforcement will be fixed as per the approved shop drawings
using the approved pre-cut and bend bars as scheduled on the approved BBS.
·
All required concrete covering for raft foundation will be followed as
per the specification
· All intersection of steel reinforcement will be tied properly and a concrete cover will be placed same strength with the required concrete.
· All intersection of steel reinforcement will be tied properly and a concrete cover will be placed same strength with the required concrete.
·
After bottom layer of rebar for raft foundation inspection request will
be submitted.
·
Top reinforcement will be inspected after the approval on bottom layer.
·
All lapping shall be in staggered position.
2.5.3.6 Raft Foundation
·
After the completion of the
curing period of the blinding concrete, waterproofing works will commence as
per approved shop drawing and Method Statement for Substructure Waterproofing
Works.
·
Checks completion of
waterproofing membrane, 50 mm protection screed shall be provided in horizontal
bottom and protection board in vertical surfaces. Water stop to be installed as
per approved shop drawings.
·
After completion and
approval of waterproofing works, formworks and reinforcement steel for the raft
foundation will be laid with approved materials and as per the approved shop
drawings. Pouring sequence of raft foundation is attached under attachment 6.5.
·
Checks will be done for the
formworks, which should be sufficiently tight, rigid and reinforcements in
details as per the approved shop drawings.
·
The surveyor will check the
coordinates,
levels
and control points for neck columns, wall and all structural members as per approved
shop drawings.
·
One coat of approved form
releasing agent will be applied to the formwork before placing the steel
reinforcement.
·
Fixing and installation of
reinforcement shall conform to BS 4466 and as per approved shop drawing.
·
All the plumbing and HVAC
box outs, bolts, inserts, wall plates, sleeves, and electrical conduits will be
placed as per the approved shop drawings and will be tied to the reinforcement
to arrest any possible movements during the concreting. For this proper
co-ordination will be done during the steel installation.
·
Final levels of the
concrete will be marked as per approved shop drawing with the help of surveyor.
·
All the precautions will be
taken for the hot weather concreting as per the ACI 305-72 specification for
hot weather concreting OR project specification.
·
(CLIENT/CONSULTANT) will be
notified at least 24 hours before each day’s operation of placing the concrete.
·
Set of concrete cube samples will be done as mentioned in appendix 6.2 Inspection
and Test Plan.
·
A designated area for
quality control check of fresh concrete delivery will be set and all concrete
deliveries will be checked and monitored by the QA/QC Engineer (Concrete
specialist) and technician from third party laboratory.
·
All the quality control
checks for the concrete such as slump, temperature will be done prior to casting. The entire QC check sheet will be
maintained for the concrete traceability.
·
Slump of the concrete
should be as per approved concrete mix design and the Concrete temp. Should not
exceed 32 C°, whereas the ambient temperature should be less than 40 C°.
·
Fog spray to the installed
reinforcement will be done to reduce the rebar temperature and allow it to cool
prior to receive concrete.
·
During placement care will
be taken, not to lose any ingredients from the concrete, any type of segregation and the displacement of the reinforcement.
·
Consolidation will be done using adequate numbers of
concrete
vibrators of appropriate size with same trained persons for each pump, and care
will be taken during the consolidation for honey combings or over vibrations.
·
Pipes will be laid above to
be used as a reference for final casting level of concrete.
·
Immediately after the
completion of the placement and concrete finishing is done, the concrete will
be covered with gauge 1000 polythene sheet. And soon as the concrete has
stiffened sufficiently wet hessian cloth will be laid and kept wet continuously
for minimum 7 days.
2.5.3.7
Formworks
·
Formwork for the raft will be placed by skilled carpenters; as per the
approved shop drawings aligned with the surveyors marking. Surveyors will mark
points for the boundaries and level of
concrete prior to pouring.
·
A kicker form shall be placed on
retaining walls, columns and other vertical structures in compliance with the
approved shop drawings.
2.5.3.8
MEP and other embedded works
·
Embedded installations will be proposed by contractor and submitted for
consultant’s approval.
2.5.3.9 Water Stopper
·
All construction joint
below the ground will be sealed using PVC water stops and swell bar.
2.5.3.10 Construction Joint
·
Care will be taken during joint installation to
maintain proper joint function and assure proper formwork support is in place
and not to destroy the joint after concrete placement.
·
A shear key will be provided for structural joints
as per structural details and shall be applied with a bonding agent as per
approved materials prior to the next casting sequence.
·
Site Engineer will submit
to the quality department the work inspection for concrete works prior target pouring schedule.
·
QC Inspector (Civil) will
check the preparation, steel placement, overlapping, anchoring as specified and
in accord to the shop drawings.
·
QC Inspector (Electrical
& Mechanical) will check the sleeves, embeds, tubes and conduits and all
items are set properly in its place.
·
QC Inspector (Civil) will
check for joints needed and preparation, existing joints preparation,
cleanliness and laittance removal, spacers and concrete cover if it is in
accordance with the Specifications and provisions of the project.
·
After the inspection and
approval of the QA/QC Inspector, works will be offered for consultant
Inspection and once approved by the consultant concrete of approved concrete
mix design will be ordered.
·
HSE TEAM will make
visual inspection for assurance of the compliance status of MS&RA in
addition to the Temporary Work Designers Calculation, PPE and
competency of the Execution Team.
Concrete
placement shall be carried out in accordance with Project specification and standards.
·
Quality control on concrete
mixtures shall be monitored to ensure smooth running, consistent pumping
operation and good quality of pumped concrete.
·
The QA/QC Department in
coordination with the Construction Department will monitor the uniformity of
the concrete materials and consistency of mixes.
·
Avoid displacing
reinforcement, ducts and anchorages, or formwork, and damage to the faces of
formwork, especially when the concrete is allowed to fall freely through the
depth of lift. Consider the effect of lift height in massive section of the
concreted area. Follow the depth of each lift every 450
mm in layer.
·
Do not spread the concrete
across the surface of open textured formwork by means of internal vibrators as
this may lead to localized honey-combing, differential mixes and inadequate
bonding between the concrete and the reinforcement.
·
All concrete shall be
compacted using a mechanical vibration process.
·
Inclined the boom of the
concrete pump to minimize free fall distance to avoid segregation, smaller size
can be used for thin walls.
·
Pumped concrete circulation
frequency shall be in line with the rate of supply and pouring rate.
·
Do not add anything to the
pump hopper during casting.
·
Pipe aligning should not be
vertically installed.
·
The concrete pump hopper
shall be always full of concrete to avoid additional air entrapment to the
mixes and maintain the pumping pressure rates.
·
If concreting should stop
for a period exceeding 30 minutes, the concrete in the pipes and hopper shall
be pumped outside the structure
2.5.3.13 Deshuttering of formwork and
Concrete Curing
·
Exposed surface of concrete shall be covered with hessian cloth and
shall be kept wet by water ponding water on the concrete surface for 7 days.
·
The hessian cloth placed on top of exposed concrete shall be wet at all
times.
2.5.3.14 Concrete Quality and Repair
·
Before any other activities will commence, upon curing is completed,
concrete surfaces shall be inspected for its quality for any defects such as
cold joints, honey combing, cracking, or surface imperfections. Any concrete
repair will be made on case-by-case and submitted under separate cover for
approval.
In summer
weather special precautions are required to avoid the rapid loss of surface
moisture and/or rapid stiffening of the concrete which prevents its proper
compaction, further to the increased heat of hydration and setting.
High
temperatures, high wind speed, low humidity are all under the precautions of
hot weather which will be the directed
cause of settlement and plastic cracking and a reduction in strength and
durability of the concrete, further to the potential formation of cold joints.
·
Concrete should not be
placed if the shade temperature exceeds 40°C on a rising thermometer.
·
At the time of placing,
concrete shall have a temperature lower than 32°C.
·
Particular attention will
be given in placing, consolidation, floating or any other mean to protect the
surface from drying prior to bleeding.
·
To prevent moisture loss
from the concrete, provide curing system immediately to open surfaces initial
floating.
·
If the surface is not to be
marked, it is best to provide the initial curing with sheets of impervious
material (polyethylene), preferably pigmented to reflect radiation, supported
away from the surface and fastened at the edges to prevent droughts.
·
Rate of evaporation from
the concrete surface shall be determined prior scheduling the pour; accordingly
the QA/QC team shall decide the pouring and protection procedure or advice for
rescheduling the pour if the rate is too high
·
Provision of shading from
wind if practicable and additional available water to keep the surface wet
after bull floating will aid in decreasing the afore-mentioned risks
·
Use of curing compounds
where
allowed, will aid in reducing the evaporation.
·
Continuous flow of concrete
is essential.
·
Increased rate of pouring
and double crews for faster application
·
Preparatory for cracking
recovery in case it developed fast prior concrete hardening
2.5.5
Consolidation
To cover
properly the congested steel structures, shove away coarse aggregates particles
from the forms, and to facilitate movements of excess water and air pockets and
entrapped air to the top surface of concrete.
·
Compact thoroughly the
concrete using applicable vibrator or other means during placing. Vibrate the
concrete until the expulsion of air has practically ceased and in a manner that
does not promote segregation.
·
Vibration on the location
of congested reinforcement, duct, sleeves, anchors, embedded items should be
carefully executed to eliminate the voids or honey combs that may affect the
appearance or integrity of the concrete.
·
Over-vibration should be
avoided to minimize the risk of forming a weak surface layer (sand streak,
scalling and lower concrete strength)
·
Consolidate concrete by
layers. The concrete will be placed in a continuous operation in two to three
lifts as per the required thickness or 450 mm high by making passes around the
perimeter or section of the wall.
·
Consolidate the concrete by
inserting Vibrator heads vertically and slowly into concrete. QA/QC
Engineer/Inspector will monitor any irregularities on the use of internal
vibrators.
·
Vibrate the flowable
concrete between 3 to 5 seconds, and up to 15 seconds for low slump/workability
concrete.
·
Pull out the vibrator
vertically and at a maximum rate of 7 cm/sec. Insertion offsets of 1.5 times
the radius of influence of the vibrator.
·
Insertion shall penetrate
slightly to the preceding layer to knit both layers together.
·
In case of external
vibrators, use those that conform to the design of the formworks to ensure
efficient compaction and to avoid surface blemishes. There must be 2 vibrators
in each concrete pump.
·
Care should be taken on the
type of vibrating procedure to account for the energy transition whenever a
permanent formwork is incorporated.
·
Extra care is required to
ensure full compaction of the concrete since this cannot be checked when the
formwork is removed.
·
Vibrate thoroughly the
concrete containing Slag cement to decrease the effect of settlement due to
self-consolidation.
·
Concrete containing fibre
reinforcement materials affect the workability and should be vibrated
thoroughly to have a good compacted mass.
Top
surfaces of concrete, buttresses and floors shall be finished to the proper
level and, if specified, to the required slopes. No holes or rough patches
shall remain. Surfaces requiring subsequent plastering or tiling shall be
rough-finished to provide a proper key for the finishing layer.
After
initial setting of the concrete, any disturbance thereon (e.g. from walking,
wheeling over or vibration of the formwork) shall be prevented until the
concrete has sufficiently hardened.
Protect
the reinforcement, anchor bolts, embeds, etc. projecting from the concrete from
disturbance during hardening of the concrete.
2.5.6.1 Screeding and Strike-Off
·
Set the level guide using
rigid metal or wood true to level and achieving the specified grade in
accordance with project requirement and as indicated in the shop drawing. Set
the level guide in a manner that it can be easily removed after screeding and
strike off process.
·
Screed surface of the last
layer with a straight edge and strike off (preferably aluminium bar) concrete
surface to correct elevation directly after vibrating the last layer.
·
One person shall be holding
the straight edge from each side, and careful backward and forward motions like
sawing and occasional tamping where required then repeating the strike off
process is helpful to maintain a smooth surface to facilitate bull floating.
·
The area to be screeded
shall not be extended very long, where it will be very difficult to control the
screeding operators and increased drying of the surface will occur. A good
practice to avoid this and speed up the available concrete is to pour a layer
up to the reinforcing level preceded by another layer to the required level or
double the finishing crews.
2.5.6.2 Bull Floating/Power Floating
·
The direct step after
screeding and strike off for all kinds of finishes.
·
Proceed to initial floating
using bull float, Darby, or modified highway straightedges before any excess
moisture or bleeding water is present on the surface to prevent dusting or
scaling. This process will set the remaining voids and drain aggregates, level
all area and cover air buckets left after screeding until we get a smooth
surface.
·
In the event that multiple
floating passes are required, each floating operation should be made
perpendicular to the direction of the previous pass.
·
Do not disturb the surface
after floating for a specified time to allow bleeding to take place.
·
Power floating can also be
applied by the time the concrete is hard enough to carry the load of the power
float. This is to eliminate the minor cracks appearing as the concrete hardens.
· Prevent
the surface from drying during this time by fog spraying or spraying softly
water incorporated with liquid solvent curing compound.
2.5.6.3 Troweling
·
Start finishing the surface
with metal trowels directly after bleeding and when the concrete is accessible,
covering the whole area. Wet the surface if necessary prior to trawling if the
surface is very dry.
·
Proceed to additional
trowelling if necessary until we get the desire surface finish.
·
Final finishing of the
concrete surface will depend on the use and the type of sub-sequent
layer/screeds. (e.g. sheet Vinyl, self-finished resin, safety flooring, carpet
tiles, etc.)
·
Re-trowelling may be needed
if plastic shrinkage crack appears in some areas after the last trawling
operation, additional water may be used to assist troweling to close the
cracks.
·
There will be at one person
to monitor those hairline cracks resulting from plastic shrinkage cracking to
cover prior to expanding.
·
Mechanical trawling is
recommended especially in hot weather and large areas
·
Two passes of mechanical
trowelling will produce a smooth finish
· When
cracking are spreading drastically only mechanical trowels will aid to recover
it prior drying of the concrete.
2.5.7
Concrete Stripping
The operations of
stripping the formwork and striking will be conducted progressively, without
impacts. The following minimum times before stripping the formworks as per the
project specifications.
Type of Formworks
|
Minimum Period Before Stripping (Times are from
Concrete Placement
|
Beam
Sides, walls and column
|
refer to specification or standards
|
Soffits
of Slab (Props left Under)
|
refer to specification or standards
|
Soffits
of beams, joists and girders (props left under)
|
refer to specification or standards
|
Props
to slabs
|
refer to specification or standards
|
Props
to beams
|
refer to specification or standards
|
Remove formwork,
for beams sides, walls, columns and similar parts of the Work that does not
support weight of concrete after cumulatively curing for 24 hours after placing
concrete provided that concrete is hard enough and not to be damaged by
form-removal operations will be discussed for the permission of consultant as
well to save time and having records to the past projects as per standards and
approval of consultants.
While
performing de-shuttering, all safety measures will be implemented. Sufficient staff will be provided to handle
the loads properly with corresponding platforms provided. The platform system will be installed
as per the manufacturer’s recommendation that would be checked from time to
time by the Scaffolding Inspectors.
Support of
tower crane in order to place and remove the formworks will be done
accordingly. The Lifting Procedure will be provided in cooperation with the HSE
Department.
It is
important to mention that boxes will be provided on designated areas for
de-nailing during removal of formworks as per the schedule provided.
Clean and
repair surfaces of forms to be reused in the work. Split, fray, delaminated, or
otherwise damaged form-facing material will not be acceptable for exposed
surfaces. Remedy for the formworks such as placing tape to the laminated
plywood could be done accordingly to prevent the product damage. Apply new
form-release agent. When forms
are reused, clean surfaces, remove fins and surplus, and tighten to close
joints. Align and secure joints to avoid offsets. Do not use patched forms for exposed concrete
surfaces unless approved.
Maintain
properly the formworks material to be re-used; the execution team shall take
into account the bearing capacity of reused forms, stiffness and safety.
0 comments: