1. TITLE Method Statement for Painting Works of wall and ceiling 2. SCOPE OF WORKS 2.1 General Description The scope and pur...

Method Statement for Painting Works of wall and ceiling

6:01 AM 0 Comments


1. TITLE

Method Statement for Painting Works of wall and ceiling

2. SCOPE OF WORKS

2.1 General Description
The scope and purpose of this method statement is to outline the general requirements and precautionary measures which should be taken into consideration during painting works to ensure that works are according to the drawings, standards and project specification.

2.2 Plant and Equipment

a. Wheel barrow
b. Drip tray
c. Pail
d. Sand paper
e. Rug cloth
f. Approved paint products
g. Brush and roller
h. Mobile scaffolding
i. Working flatforms

2.3 Materials

S.N
Material
Manufacturer
/Supplier
Status
1
Painting systems -
Input the reference submittal
supplier name of paint
is it approved or rejected

2.4    Site Planning and Preparation

2.4.1           Prior to start the work, an execution clearance will be obtained from MEP & Site Engineers to ensure proper coordination. Proper planning of execution as per area of installation shall be made.
2.4.2           Before painting commences all surfaces in the work area are to be washed and scrubbed clean of debris and every possible precaution taken to keep down dust. No paint is to be applied to surfaces structurally or superficially damp and all surfaces must be ascertained to be free from condensation, efflorescence, etc., before the application of each coat.
2.4.3           All items not required to be painted (e.g., ironmongery) are first to be fitted and then removed or covered before any painting preparation commences. The fittings shall be refixed in position when all painting is completed.
2.4.4           Brushes, pails, kettles, etc., used in carrying out the work are to be clean and free from foreign matter. They are to be thoroughly cleaned before being used for different types or classes of material.
2.4.5           The surface is first to be scraped to remove mortar splashes, etc., and then made good, cutting out all defective work and repairing with plaster or render of the same type as previously used.
2.4.6           The surface is then to be sanded using progressively finer grades of paper until perfectly smooth.
2.4.7           Wipe the surface area with dry rug to remove all dust or clean by compressor.

2.5    Work Methodology

       Parking Area Walls
2.5.1           Follow the approved painting system as per specification.
a.    Anti-carbonation system (Basement Area-Car parking) – Painting system
·         Primer 
·         Final Top coats
Note: If filling is required apply filler prior to application of paint

b.    Color must be selected and approved by client.

2.5.2           Prepare a mock-up sample of the complete system and submit to consultant for inspection and approval prior to proceed with the full works.
2.5.3           Application of one coat Primer (as per approved paint system) shall be applied after the substrate moisture content is attained in order not to affect the performance of the system.
2.5.4           Ensure that substrate is free of any voids or uneven surface prior to application of primer. Frequent visual inspection must be conducted in all areas.
2.5.5           Apply first & second coat of top coat (as per approved paint system)  as per the approved color.
2.5.6           Finish coats will be applied as an even film over all exposed surfaces, avoiding brush marks, sags, runs and other defects. Where two finish coats are specified the second coat shall be applied within 12 hours of the first.
2.5.7           Fence off the areas from traffic workers until the paint is fully dry. Put warning sign at appropriate locations.

  Parking Ceilings
2.5.8           Ensure that all joint of cement board is covered with joint compound with joint tape to ensure it will be free of cracks.
2.5.9           Application of one coat Primer (as per approved paint system)  shall be applied after the substrate moisture content is attained in order not to affect the performance of the system.
2.5.10        Ensure that substrate is free of any voids or uneven surface prior to application of primer. Frequent visual inspection must be conducted in all areas or apply 38810-11630 Maestro Pro Filler if applicable.
2.5.11        Apply first & second coat of top coat (as per approved paint system)  as per the approved color.
2.5.12        Finish coats will be applied as an even film over all exposed surfaces, avoiding brush marks, sags, runs and other defects. Where two finish coats are specified the second coat shall be applied within 12 hours of the first.
2.5.13        Fence off the areas from traffic workers until the paint is fully dry. Put warning sign at appropriate locations.

Field Quality

a.       Ensure that substrate moisture content is properly attained.
b.       Ensure the evenness of painted walls.
c.        Ensure that approved paint material is use on site.
d.       Supervise and ensure the Quality and acceptable workmanship.

Housekeeping

            a.            Clean exposed surfaces of dirt, stains, mortar splashes and other blemishes.
b.                   Working areas will be kept clean by disposing the waste materials at the designated work areas.