Method Statement for repairing of tie rod hole
1. TITLE
Method Statement for repairing of tie rod hole.
2. SCOPE OF WORKS
2.1
General Description
·
The
scope and purpose of this method statement is to outline the general
requirements and precautionary measures which should be taken into
consideration for the proper repairing of tie rod holes to ensure that works
are according to the drawings, standards and project specification.
2.2
Plant and Equipment
§
Approved repair material
§
Electric Mixing paddle
§
Spatula
§
Hilti jack hammer
§
Grinder or Cutting torch
2.3
Materials
|
S.N
|
Material
|
Status
(approved or Rejected)
|
|
|
1
|
Repair Grout material
|
|
|
|
2
|
Potable water
|
|
|
|
3
|
Curing compound
|
|
|
|
|
2.4.1
Clean the concrete surface or
flattened the surface using grinder.
2.4.2
Cut the area around the steel
2.4.3
Cut the tie rod using cutting
torch or grinder; ensure the tie rod is offset by at least 10mm from the concrete
surface.
2.4.4
Prepare the slurry by mixing
the approved repair materials and water as
per manufacturer’s recommendation. Use electrical mixing paddle for mixing.
2.4.5
Fill in the chipped area and
protect the mortar from rapid drying by applying curing compound.
2.4.6
All activities in elevated
areas shall be fully coordinated with HSE department. Ensure that the working
flat form is inspected and approved by HSE officer.
2.4.7
All waste materials shall be
place in a separate bucket and must be segregated in other waste items to avoid
contamination.