Method Statement for Tile Installation
1. TITLE
Method Statement for Installation of
Wall and Floor Tiles
2. SCOPE OF WORKS
2.1 General Description
The Scope of this method statement is
to outline the general requirements and precautionary measures which should be
taken into consideration during installation of wall and floor tiles and to
ensure that works are according to approved shop drawings, standards and
project specification.
2.2 Plant and
Equipment
·
Masonry trowels and other hand tools
·
Mechanical Mixer
·
Electric Grinder
·
Forklift
·
Grinder / Cutter
2.3 Materials
SN
|
Material
|
Reference
|
Status
|
1
|
Ceramic Tiles
|
||
2
|
Porcelain Tiles
|
||
3
|
Tile Adhesive
|
||
4
|
Tile grout
|
2.4 Site Planning and
Preparation
·
All concrete surface where the tiles
must be installed shall be free from any concrete laitance and any foreign
materials.
·
All surface preparation and
waterproofing inspection (for wet areas) shall be completed & approved by
Engineer prior to installation.
·
All materials and shop drawing shall
be approved by Engineers prior to any activities.
·
Mock-up Inspection must be done prior
to start of Tile Installation.
·
All HSE Permits shall be secured ahead
of the time.
2.5.1 Material Storage and
Handling
a.
The materials delivered at site shall
be carefully off-loaded as per manufacturer’s instructions by deploying
necessary / adequate manpower in such a way that no damage is caused. (It will
be off loaded by the supplier using their own lifting equipment and gears.)
b.
Store the materials on elevated
platforms, under cover & in a dry location.
c.
It shall be ensured that the delivered
materials are in compliance with the approved material submittal.
d.
Any discrepancies or damages found
shall be notified and reported to the Engineers for further action,
notification shall be sent to the supplier.
e.
Material found not suitable for site
use shall be removed from the site immediately and replaced with suitable
material.
2.5.2 Wall Tile
Installation
a.
Prior to start installation
activities, refer to the approved shop drawings related to the installation
area & ensure that materials were as per approved material submittal.
b.
Incoming material inspection must be
done with the consultant prior to installation to verify its compliance to the
approved material submittal.
c.
Waterproofing Inspection and Leak
test on wet areas shall be completed prior to start installation.
d.
MEP Clearance on all areas related to
the installation must be obtained.
e.
Tile edges will be accurately cut to
a close fit where necessary, at abutments, around electrical pipes and other openings.
f.
Movement Joints not less than 6 mm
wide are to be provided as per approved shop drawing.
g.
Corner Trim to be used to be used for
fixation.
h.
Tile adhesive shall be prepared and applied as per manufacturers
recommendation.
i.
The tiles are to be pressed firmly
into the adhesive with a twisting/sliding action, tapped firmly into position
and cleaned as soon as the bedding is complete.
j.
The finished surface of the tiles
should be plumb and true such when checked with a 3 m straight edge no gap exceeds
3 mm.
k.
The joints shall be even,
approximately 2 mm wide and where tile without spacer lugs are used, spacer pegs
of suitable and even thickness shall be inserted between the tiles as the work
proceeds.
l.
The joints are to be grouted by
approved grouting material after the adhesive has set and not less
than 48 hrs after fixing. The grout shall be well worked into the joints so that
they are completely filled and finished flush.
m.
Excess/Surplus grout shall be cleaned
off using damped or wet cloth.
n.
Final Inspection shall be requested
for Engineers approval and acceptance.
2.5.3 Floor Tiles
Installation
a.
Prior to start installation
activities, refer to the approved shop drawings related to the installation
area & ensure material are as per approved material submittal.
b.
Waterproofing Inspection and Leak
test on wet areas shall be completed prior to start installation.
c.
Incoming material inspection must be
done with the consultant prior to installation to verify its compliance to the approved
material submittal.
d.
After casting of
required thickness of screed as per design requirements, surface shall be
suitable for floor coverings, areas to be tiled shall be cleaned and dampened
until absorption ceases and the level of the finished floor shall be
established by the surveyor.
e.
MEP Clearance on all areas related to the installation
must be obtained.
f.
Double direction horizontal layout of
tiles to be installed must be checked and approved by the Engineer prior to
proceeding the installation.
g.
Tile adhesive shall be prepared and applied as per manufacturers
recommendation.
h.
The bedding mortar for tiles 10 mm
thickness or less are used in which case the bedding is not to exceed 15 mm
shall be levelled and tamped with a straight edge board.
i.
The bedding mortar is to be lightly
dusted with dry cement sprinkled lightly troweled level until the surface
becomes damp. The tiles are then to be laid on the bedding and beaten firmly
into position with a wooden beater to ensure a true surface and contact between
the tiles and bedding is complete.
j.
Installed floor tiles shall be
correctly positioned at the time they are placed with joints using tile spaces
as specified on the approved shop drawings.
k.
Tiles are to be neatly and accurately
cut to a close fit where necessary at abutments and around outlets, pipes and
other MEP services.
l.
Tile to be laid level or to 1% slopes
(in wet areas), if required. Tolerance in level for a flat floor to be maximum
of ±3 mm. Particular care is to be taken in wet areas to prevent low spots.
m.
Prior to application of grout, ensure
proper cleaning of joint.
n.
Grouting joints to be carried out
within a period of 24 hrs of the of the laying of the tiles so that the grout
will attach each self firmly to the bedding. Avoid disturbing the tiles,
walking boards are to be used during grouting application.
o.
Remove surplus grout with a sponge,
for dry grout use cloth for cleaning.
p.
Prohibit foot and wheel traffic tiled
floors for at least seven days after grouting is completed.
q.
Final Inspection shall be requested
for Engineers approval and acceptance.
0 comments: